Earthworks in Saverne

Saverne

Earthworks Site in Saverne for Le Géant des Beaux-Arts

SPIESS carried out earthworks in Saverne to prepare for the expansion of a building. This major project is led by Buraglio Architecte.

About ten days of work were needed to clear 4,000 m³ of soil, level the ground, and dig the foundations.

Two machines equipped with onboard GPS were used for this project:

  • Bull Liebherr 726
  • Pelle Liebherr 926 Compact


Thanks to the guidance system, the operators can perform maneuvers with precision and monitor the excavation levels in real time. This technology allows our teams to optimize their work time and deliver highly accurate results for our clients.